• healthetank@lemmy.ca
    link
    fedilink
    arrow-up
    1
    ·
    3 months ago

    I work on the linear infrastructure side as a consultant - any particular reason that they took so long to award the tender? That seems extreme given that I regularly work with municipalities and tendering processes, and its a pretty well oiled machine - 1 month is about as long as I’ve ever seen the award be stretched, unless the engineering cost estimate was waaaay below the bids and they had to secure additional funding.

    • pipsqueak1984@lemmy.ca
      link
      fedilink
      arrow-up
      2
      arrow-down
      2
      ·
      edit-2
      3 months ago

      They needed the government funding approved in order to award the contract and the approval process (which required all bids to be submitted, not just the planned awarded one) unexpectedly took 9 months with the feds. It wasn’t a municipal project either, it was a local nonprofit org.

      I work a lot with the architect that is overseeing the project and not once did they complain about having to submit extra info to the fed (and I have a pretty solid relationship with them so while not completely professional to complain like that it’s the type of thing that would have come up in side conversations in-person when meeting up for other projects)